ACS Data Center Dallas TX

  • acs-datahall-cropped
  • acs-data-center-high-res-cropped
  • acs-before-two-higher-res-cropped
  • acs-switchgear-cropped
  • acs-switchgear-2-cropped
  • before-three-higher-res-cropped
  • data-center-floor-distribution-panels-cropped

AT A GLANCE: 24 Weeks Start-to-Finish - Abandoned Warehouse into Active Data Center

OVERVIEW
With a 24 week, start-to-finish deadline, an existing, abandoned warehouse needed to be converted into an active 12,500 SQ FT raised floor data center with 1.2 MW of redundant critical power and a new medium voltage sub-station. Project delivered on-time and on budget.

CRITICAL EQUIPMENT

  • 3 x 750kVA Parallel UPS System expandable to 4 modules
  • 3 x 1.5 MW parallel generator system expandable to 4 generators
  • 12 x 30Ton computer room air conditioners and condensers
  • 10 x 125kVA power distribution units
  • 1 x 4000A Automatic Transfer Switch
  • 3 x 1200A Automatic Transfer Switch

SERVICES PROVIDED

  • Design & Engineering
  • Construction & Project Management
  • Data Center Equipment
  • Startup & Commissioning